2025-54 Resolution of the Council, re: Award of Contract to Crossman Engineering for the Wastewater Facilities Plan Update, funding from the Sewer Fund and authorizing the Finance Director to execute the contract on behalf of the Town.
Middletown
Resolution
THE TOWN OF MIDDLETOWN
RESOLUTION
OF THE
COUNCIL
No: 2025-54
RESOLVED:
The contract for the WASTEWATER FACILITIES PLAN UPDATE is hereby awarded to CROSSMAN ENGINEERING for the amount not to exceed ONE HUNDRED EIGHTY-FOUR THOUSAND SIX HUNDRED-EIGHTY DOLLARS AND ZERO CENTS,
and
BE IT FURTHER RESOLVED:
That funding for the WASTEWATER FACILITIES PLAN UPDATE is from the Sewer Fund fund balance,
and
BE IT FURTHER RESOLVED:
That the Finance Director is authorized hereby to execute said contract on behalf of the Town of Middletown.
JULY 7, 2025
READ AND PASSED IN COUNCIL
Wendy J. W. Marshall, MMC
Town Clerk