Jun. 10, 2026 - Building Committee Meeting

Middletown · School Committee June 10, 2026 Official source ↗ Retrieved Jul 22, 2026

Integrated electronic security contract recommendation; MS/HS construction progress, Valley and Forest Avenue project updates

What happened

Committee approved May minutes, recommended awarding a $1,119,480 Integrated Electronic Security System contract, heard MS/HS construction, Valley and Forest Avenue updates, budget and schedule reports, and set next meeting for July 15, 2026.

Budget/MoneyPublic SafetySchools
2Formal actions
2Policy decisions
$1.12MContracts

Key actions 1

  1. Award contract for Middle/High School security system to National Security Fire Alarm Systems Passed · 12–0

    The town recommended awarding the Integrated Electronic Security System contract for the Middle/High School to National Security Fire Alarm Systems for $1,119,480.

Key decisions 30

Approve the May 13, 2026 meeting minutes

Passed · 11–0

This item records accepting the written minutes from the May 13, 2026 meeting.

Result Passed 11–0
Motion by Bill Nash
Seconded by Peter Connerton
Individual votes Not recorded
Source wording

Accept the meeting minutes from May 13, 2026

See it in the full record

Gilbane monthly dashboard information shared

Justin Bernard shared information from Gilbane’s monthly dashboard report to inform updates on safety, schedule, document control, and financial status.

Informational item — no recorded vote.

Infrastructure
Source wording

Justin Bernard shared information from Gilbane’s monthly dashboard report.

See it in the full record

Project has two recordable injuries; one recent ankle injury

Justin Bernard reported the project now has two recordable injuries; another iron worker twisted their ankle on the stairs while prepping for concrete placement.

Informational item — no recorded vote.

Public Safety
Source wording

Justin explained that the project is now up to two recordable injuries. Another iron worker got hurt by twisting their ankle on the stairs while prepping for the concrete placement.

See it in the full record

Gilbane held a safety session with subcontractor

Gilbane held a safety standout with the subcontractor involved after recent incidents to try to mitigate additional injuries going forward.

Informational item — no recorded vote.

Public Safety
Source wording

Gilbane has had a safety standout with this vendor to try to mitigate any additional injuries moving forward.

See it in the full record

MEP risers and masonry façade work started at high school wing

Mechanical, electrical, and plumbing (MEP) risers and masonry façade work began last week on the south and west sides of the high school wing. These are listed as upcoming construction milestones.

Informational item — no recorded vote.

Infrastructure
Source wording

Some upcoming milestones include Mechanical Electrical Plumbing (MEP) Risers and the Masonry Façade, which started on the south and west sides of the high school wing last week.

See it in the full record

Mid-May drone flyover and recent construction photos shared

Justin shared a drone flyover from mid-May and walked the group through recent photos to show construction progress.

Informational item — no recorded vote.

Infrastructure
Source wording

Drone Flyover – Justin shared the drone flyover from mid-May and walked the group through some recent photos of construction progress.

See it in the full record

Gilbane presentations to students were well received

Gilbane gave presentations to groups of high school and Gaudet School students, and staff reported that the students loved the presentations.

Informational item — no recorded vote.

Schools
Source wording

Gilbane recently gave a couple of presentations to groups of high school and Gaudet School students. It was a big hit; the students loved it.

See it in the full record

Four Week Look Ahead report

A Four Week Look Ahead was presented that described upcoming exterior and interior work, Valley mobilization, and Forest Avenue design progress.

Informational item — no recorded vote.

Source wording

Four Week Look Ahead

See it in the full record

Award contract for Middle/High School security system to National Security Fire Alarm Systems

Passed · 12–0

The town recommended awarding the Integrated Electronic Security System contract for the Middle/High School to National Security Fire Alarm Systems for $1,119,480. The recommendation was reported by Ed Collins and Colliers Project Leaders and the measure passed 12–0.

Result Passed 12–0
Motion by Don Morin
Seconded by Bill Nash
Individual votes Not recorded
Infrastructure
Source wording

Recommend awarding the Integrated Electronic Security System contract to National Security Fire Alarm Systems in the amount of $1,119,480

See it in the full record

Meeting called to order at 4:30 pm; attendance noted

The meeting was called to order at 4:30 pm by Ed Brady. Eleven (11) of thirteen (13) voting members were present or represented by an alternate.

Informational item — no recorded vote.

Source wording

The meeting was called to order at 4:30 pm by Ed Brady. Eleven (11) of thirteen (13) voting members were present or represented by an alternate.

See it in the full record

Colliers Project Leaders representative attended

Justin Bernard of Colliers Project Leaders was present and provided project updates and a recommendation to award the security contract.

Informational item — no recorded vote.

Source wording

Also present: Justin Bernard, Colliers Project Leaders

See it in the full record

Additional project team members attended via Zoom

Colin McCarthy (Colliers Project Leaders), Matt LaRue and Tina Stanislaski (HMFH Architects), and Ed Cifune and Emma Osborne (DBVW Architects) attended the meeting via Zoom and participated in project discussions.

Informational item — no recorded vote.

Source wording

Present via Zoom: Colin McCarthy, Colliers Project Leaders; Matt LaRue, Tina Stanislaski, HMFH Architects; Ed Cifune and Emma Osborne, DBVW Architects

See it in the full record

Valley Elementary Project Update

A brief update titled "Valley Elementary Project Update" was placed on the agenda under Other business. No further details, discussion, or actions are recorded in this bundle.

Informational item — no recorded vote.

See it in the full record

Valley Elementary Summer 2026 preplanning update

Justin gave an overview of planned work at Valley Elementary for Summer 2026, listing the primary scopes and additional items under consideration for that season.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Summer 2026 Preplanning

See it in the full record

Valley Elementary: nurse’s suite prioritized for Summer 2026

Justin reported that the nurse’s suite remains a primary focus of the Valley Elementary Summer 2026 work.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Nurse’s Suite

See it in the full record

Valley Elementary: first‑floor bathrooms work planned

Justin reported that first‑floor bathrooms are a primary focus of the Summer 2026 work at Valley Elementary.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — First Floor Bathrooms

See it in the full record

Valley Elementary: elevator shaft work planned

Justin reported that elevator shaft work is included as a primary focus for Valley Elementary during Summer 2026.

Informational item — no recorded vote.

InfrastructureSchools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Elevator Shaft

See it in the full record

Valley Elementary: selective painting included for Summer 2026

Justin reported that painting in select areas is planned as part of the Summer 2026 work at Valley Elementary.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Painting in select areas

See it in the full record

Valley Elementary: acoustical ceiling tile added

Justin said Acoustical Ceiling Tile (ACT) in select areas was recently added to the Summer 2026 work list for Valley Elementary.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Acoustical Ceiling Tile (ACT) in select areas

See it in the full record

Valley Elementary: chair lift replacements noted

Justin said two chair lift replacements were added to the Summer 2026 scope, and that a vertical lift might not arrive in time to be installed this summer.

Informational item — no recorded vote.

InfrastructureSchools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Two chair lift replacements. The vertical lift might not arrive in time to get installed this summer.

See it in the full record

Valley Elementary: column enclosures at gym and cafeteria

Justin reported column enclosures at the gym and cafeteria were added to the Summer 2026 work list for Valley Elementary.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Column enclosures at the gym and cafeteria.

See it in the full record

Valley Elementary: roof replacements in select areas

Justin said roof replacement in select areas was added to the Summer 2026 scope for Valley Elementary.

Informational item — no recorded vote.

InfrastructureSchools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Roof replacement in select areas.

See it in the full record

Valley Elementary: Bentley to mobilize June 25, 2026

Justin reported that Bentley plans to mobilize on June 25, 2026, the day after the final day of school.

Informational item — no recorded vote.

Schools
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Bentley plans to mobilize on June 25th, the day after the final day of school.

See it in the full record

New construction rep assigned to Valley Elementary

Colliers is adding Martin Warrington as another construction representative. He will focus on work at Valley Elementary, then shift to assist at the Middle-High School during the school year, and return to Valley Elementary in summer 2027.

Informational item — no recorded vote.

Infrastructure
Source wording

Justin provided the following update on the work at Valley Elementary — Primary Focus for summer of 2026 is still — Some items recently added for this summer include — Colliers is bringing another construction representative to the team. Martin Warrington will focus on the work at Valley Elementary and will then shift over to the Middle-High School to assist Ryan during the school year, before going back to Valley Elementary during the summer of 2027.

See it in the full record

Forest Avenue Elementary project noted

A brief heading listed the Forest Avenue Elementary Project Update; no details were provided in this entry.

Informational item — no recorded vote.

Follow-up Required
Source wording

Forest Avenue Elementary Project Update

See it in the full record

Forest Avenue schematic estimate will be reconciled

Justin said the overall budget hasn’t changed since last month but costs for the work at Forest Avenue are expected to change; reconciliation of the schematic design estimate occurred on June 8 and will continue with an update planned in July.

Informational item — no recorded vote.

Budget/MoneyInfrastructure
Source wording

Justin shared the following budget update, stating that the budget hasn’t changed since last month, but cost for the work for Forest Avenue is expected to change.

See it in the full record

Welding shop CTE program update

Superintendent William Niemeyer gave an update on the MSHS Welding Shop CTE program and noted plans related to the program’s implementation.

Informational item — no recorded vote.

Schools
Source wording

MSHS Welding Shop CTE Program Update

See it in the full record

Cultural/Historical/Memorial subcommittee continuing work

Bill Nash reported the subcommittee is continuing to meet with the design team on colors and graphics and is meeting families about memorials; a fuller update will be provided in July.

Informational item — no recorded vote.

Follow-up Required
Source wording

Cultural, Historical, Memorial Subcommittee Update

See it in the full record

Design details: finishes and graphics chosen

The committee and design team have been meeting and have selected colors for floors, paint, and tile, and have reviewed graphics for the project.

Informational item — no recorded vote.

Infrastructure
Source wording

Bill Nash stated that the committee continues to meet with the design team. Colors for the floors, paint, and tile have been made and graphics have been reviewed.

See it in the full record

Next Building Committee meeting: July 15 at 4:30pm

The next Building Committee meeting is scheduled for July 15th at 4:30pm.

Informational item — no recorded vote.

Source wording

The next Building Committee meeting will be on July 15th at 4:30pm.

See it in the full record

Contracts & money 4

Estimated potential change orders total $954,451 — The project has Estimated PCO’s: $ 954,451. The team is working to get these closed out as soon as possible.
Budget/Money
Source wording

Estimated PCO’s: $ 954,451. The team is working to get these closed out as soon as possible.

See it in the full record

General Fund appropriation recorded — The record shows a $484,308 appropriation from the General Fund toward the project funding.
Budget/Money
Source wording

$484,308 Appropriation from General Fund

See it in the full record

Project budget line items shown — The project budget was listed as $200,049,925 with line items: Middle/High School $173,623,000; Valley Elementary $20,182,100; and Forest Avenue Elementary $6,244,825 (estimated pre-design budget).
Budget/MoneyInfrastructure
Source wording

Project Budget: $200,049,925 — Middle/High School: $173,623,000 — Valley Elementary: 20,182,100 — Forest Avenue Elementary: $6,244,825 (estimated pre-design budget)

See it in the full record

Total anticipated costs excluding contingencies — Total Anticipated Costs (excluding Contingences) were reported as $189,678,500.
Budget/Money
Source wording

Total Anticipated Costs (excluding Contingences): $189,678,500

See it in the full record

Communications 9

Recommendation was $40,520 below budgeted amount

Justin Bernard reported that the recommendation to award the Integrated Electronic Security System contract to National Security Fire Alarm Systems in the amount of $1,119,480 is $40,520 below the budgeted amount of $1,160,000.

Budget/Money
Source wording

Justin Bernard informed the Building Committee that Middletown’s Shared Facilities Director Ed Collins and Colliers advise the Building Committee to recommend awarding the Integrated Electronic Security System contract to National Security Fire Alarm Systems in the amount of $1,119,480, which is $40,520 below the budgeted amount of $1,160,000.

See it in the full record

Town negotiated directly with a sole-source security vendor

The Town negotiated directly with National Security Fire Alarm Systems as a sole-source vendor so the same company will serve both school and municipal buildings, which the Town expects will allow for better integration, security, and local monitoring.

Infrastructure
Source wording

The Town negotiated directly with a sole source vendor, National Security Fire Alarm Systems, as they are in the process of becoming the sole security vendor for the Town for both the school and the municipal buildings, which will allow for better integration, better security and better monitoring as all the monitoring is local.

See it in the full record

Administrative staff and public walkthroughs planned

Some administrative staff completed a site walkthrough last week. Superintendent Niemeyer and Principal Sweet are planning dates to invite local elected officials and members of the public for walkthroughs in the near future.

Public CommentFollow-up Required
Source wording

Some members of the administrative staff were able to walk through the site last week as well. Superintendent Niemeyer and Principal Sweet are planning some dates to invite local elected officials and members of the public for a walkthrough in the near future.

See it in the full record

Valley Elementary new water service design

Justin provided an update on the new water service design for Valley Elementary, noting interaction with Newport Water and work to address their comments.

Infrastructure
Source wording

Justin provided the following update on the work at Valley Elementary — New Water Service Design

See it in the full record

Project team met with Newport Water on May 18

Justin reported that the project team was able to meet with Newport Water on May 18th to discuss the Valley Elementary water service.

Infrastructure
Source wording

Justin provided the following update on the work at Valley Elementary — The project team was able to meet with Newport Water on May 18th.

See it in the full record

Newport Water email listed additional requirements on May 19

Justin said an email from Newport Water was received on May 19th that contained a list of additional requirements needed to get the water for the new fire service at Valley Elementary approved.

Infrastructure
Source wording

Justin provided the following update on the work at Valley Elementary — An email from Newport Water was received on May 19th. It contained a list of additional requirements to get the water for the new fire service at Valley Elementary approved.

See it in the full record

Design team addressing Newport Water comments for resubmission

Justin reported the design team is working on addressing Newport Water’s comments so they can finalize documents for resubmission and approval.

InfrastructureFollow-up Required
Source wording

Justin provided the following update on the work at Valley Elementary — The design team is working on addressing the comments for final resubmission and approval.

See it in the full record

Donor meeting planned for welding shop funding

Superintendent Niemeyer said he will meet with a donor on Monday to discuss funding for the implementation phase of the welding shop project.

SchoolsBudget/Money
Source wording

Superintendent Niemeyer informed the Building Committee that he will be meeting with a donor on Monday to discuss funding for the implementation phase of the project.

See it in the full record

Planning memorial elements for the new middle-high school

The subcommittee has met with families of people memorialized at other schools (Gaudet school, Clark gymnasium, Krupowicz planetarium) and plans to include some form of memorial in the future middle-high school; a more comprehensive Cultural/Historical/Memorial update will be brought to the July meeting.

Public CommentFollow-up Required
Source wording

Bill added that the subcommittee has met with families of those who have been memorialized in the schools, such as the Gaudet school, Clark gymnasium and Krupowicz planetarium, and the plan will be to continue with some sort of memorial in the future middle-high school.

See it in the full record

Also in the record 2

schematic design estimate reconciliation

From the record
Meeting attendance and schematic design reconciliation

Meeting attendance is recorded for the Michael S. Pinto Conference Room, listing Edward Brady (Chair, Community Member); William Nash (Vice Chair, School Committee Clerk); William Niemeyer (Superintendent of Schools); Tami Holden (School Committee Member); Thomas P. Welch, III (Town Council Vice President); Peter Connerton (Town Council Member); Donna Sweet (Middletown High School Principal); Michelle Fonseca (Asst Superintendent for Teaching and Learning); Shawn Brown (Town Administrator, Local Budget Official); Don Morin (Secretary, Community Member); Marc Thayer (Community Member); Dan Thibeault (Community Member); Gregory Huet (Alternate Member of School Committee); Christopher Logan (Alternate Town Council Member); Jerry Haas (Gaudet Middle School Principal); and Marc Tanguay (Town Finance Director, Alt. Local Budget Official). Tami Holden arrived at 4:32pm; Tom Welch arrived at 5:13pm. On Monday June 8th there was a schematic design estimate reconciliation meeting with HMFH's third party estimator and the team from Bentley, and reconciliation will continue through the end of next week.

Source wording

Michael S. Pinto Conference Room | Present | Voting Member | Name | Title | | X | Yes | Edward Brady | Chair, Community Member | | X | Yes | William Nash | Vice Chair, School Committee Clerk | | X | Yes | William Niemeyer | Superintendent of Schools | | X | Yes | Tami Holden | School Committee Member | | X | Yes | Thomas P. Welch, III | Town Council Vice President | | X | Yes | Peter Connerton | Town Council Member | | X | Yes | Donna Sweet | Middletown High School Principal | | X | Yes | Michelle Fonseca | Asst Superintendent for Teaching and Learning | | R | Yes | Shawn Brown | Town Administrator, Local Budget Official | | X | Yes | Don Morin | Secretary, Community Member | | X | Yes | Marc Thayer | Community Member | | X | Yes | Dan Thibeault | Community Member | | N | Alternate | Gregory Huet | Alternate Member of School Committee | | N | Alternate | Christopher Logan | Alternate Town Council Member | | P | Alternate | Jerry Haas | Gaudet Middle School Principal | | X | Alternate | Marc Tanguay | Town Finance Director, Alt. Local Budget Official | Tami Holden arrived at 4:32pm; Tom Welch arrived at 5:13pm 4.4.1 On Monday June 8th there was a schematic design estimate reconciliation meeting with HMFH's third party estimator and the team from Bentley. Reconciliation will continue through the end of next week.

See it in the full record

project cost and schedule update

From the record
Project cost status, schedule change, and upcoming construction work

Initial estimates are a little higher than originally forecasted but are within available funding and are expected to be within the RIDE approved MOA to secure 55% reimbursement from the state. The building envelope completion date was moved from March 30, 2027 to February 17, 2027. The MS/HS project will continue with exterior utilities & drainage, concrete slabs, Air Vapor Barrier, exterior masonry, roofing, spray fireproofing, interior & exterior framing and MEP fire protection rough-in.

Source wording

4.4.3 The initial estimates are a little higher than originally forecasted, but the cost is within our available funding, and the cost is expected to be within the RIDE approved MOA to secure 55% reimbursement from the state. 4.5.1 Justin shared that a lot of the milestones didn't change, except for the building envelope completion date at the middle high school. Gilbane pulled in that date several weeks from the schedule that was submitted last month. Last month it was March 30, 2027, and they pulled that date back to February 17, 2027. 4.7.1 The MS/HS project will continue with exterior utilities & drainage, concrete slabs, Air Vapor Barrier, exterior masonry, roofing, spray fireproofing, interior & exterior framing and MEP fire protection rough-in.

See it in the full record

Read the full text the original record, verbatim

Official record ↗

Approved July 15, 2026

MPS BUILDING COMMITTEE MEETING

Oliphant Administration Building

Michael S. Pinto Conference Room

26 Oliphant Lane, Middletown, RI 02842

June 10, 2026, 4:30pm

Members in Attendance:

| Present | Voting Member | Name | Title |
| X | Yes | Edward Brady | Chair, Community Member |
| X | Yes | William Nash | Vice Chair, School Committee Clerk |
| X | Yes | William Niemeyer | Superintendent of Schools |
| X* | Yes | Tami Holden | School Committee Member |
| X | Yes | Ed Collins | Middletown Shared Facilities Director |
| X* | Yes | Thomas P. Welch, III | Town Council Vice President |
| X | Yes | Peter Connerton | Town Council Member |
| X | Yes | Donna Sweet | Middletown High School Principal |
| X | Yes | Michelle Fonseca | Asst Superintendent for Teaching and Learning |
| R | Yes | Shawn Brown | Town Administrator, Local Budget Official |
| X | Yes | Don Morin | Secretary, Community Member |
| X | Yes | Marc Thayer | Community Member |
| X | Yes | Dan Thibeault | Community Member |
| N | Alternate | Gregory Huet | Alternate Member of School Committee |
| N | Alternate | Christopher Logan | Alternate Town Council Member |
| P | Alternate | Jerry Haas | Gaudet Middle School Principal |
| X | Alternate | Marc Tanguay | Town Finance Director, Alt. Local Budget Official |

X = Present/Voting; R=Represented; P=Present/Non-voting; N=Not Present

  • Tami Holden arrived at 4:32pm; Tom Welch arrived at 5:13pm

1. The meeting was called to order at 4:30 pm by Ed Brady. Eleven (11) of thirteen (13) voting members were present or represented by an alternate.

2. Also present: Justin Bernard, Colliers Project Leaders

3. Present via Zoom: Colin McCarthy, Colliers Project Leaders; Matt LaRue, Tina Stanislaski, HMFH Architects; Ed Cifune and Emma Osborne, DBVW Architects

· MOTION: Bill Nash moved to accept the meeting minutes from May 13, 2026, and Peter Connerton seconded.

· DISCUSSION: None

· VOTE: The motion passed unanimously (11-0).

3.1 No Update

4.1 Review of Recommendation to Award – MSHS Integrated Electronic Security System

4.1.1 Consider and Vote to Award the Contract for Integrated Electronic Security System for the new Middle/High School

· Justin Bernard informed the Building Committee that Middletown’s Shared Facilities Director Ed Collins and Colliers advise the Building Committee to recommend awarding the Integrated Electronic Security System contract to National Security Fire Alarm Systems in the amount of $1,119,480, which is $40,520 below the budgeted amount of $1,160,000.

· The Town negotiated directly with a sole source vendor, National Security Fire Alarm Systems, as they are in the process of becoming the sole security vendor for the Town for both the school and the municipal buildings, which will allow for better integration, better security and better monitoring as all the monitoring is local.

· MOTION: Don Morin moved that the Building Committee make a recommendation to award the Integrated Electronic Security System contract to National Security Fire Alarm Systems in the amount of $1,119,480, which is $40,520 below the budgeted amount of $1,160,000. Bill Nash seconded the motion. The motion passed on a unanimous vote (12-0).

4.2 MSHS Project Update

· Justin Bernard shared information from Gilbane’s monthly dashboard report.

· Safety Update

· Justin explained that the project is now up to two recordable injuries. Another iron worker got hurt by twisting their ankle on the stairs while prepping for the concrete placement.

· Gilbane has had a safety standout with this vendor to try to mitigate any additional injuries moving forward.

· Document Control

· 183 Submittals in review

· 14 RFI’s in review

· Schedule

· Some upcoming milestones include Mechanical Electrical Plumbing (MEP) Risers and the Masonry Façade, which started on the south and west sides of the high school wing last week.

· Financial Status

· Estimated PCO’s: $ 954,451. The team is working to get these closed out as soon as possible.

· Progress Photos

· Drone Flyover – Justin shared the drone flyover from mid-May and walked the group through some recent photos of construction progress.

· Gilbane recently gave a couple of presentations to groups of high school and Gaudet School students. It was a big hit; the students loved it.

· Some members of the administrative staff were able to walk through the site last week as well. Superintendent Niemeyer and Principal Sweet are planning some dates to invite local elected officials and members of the public for a walkthrough in the near future.

4.3 Valley Elementary Project Update

· Justin provided the following update on the work at Valley Elementary:

· New Water Service Design

· The project team was able to meet with Newport Water on May 18th.

· An email from Newport Water was received on May 19th. It contained a list of additional requirements to get the water for the new fire service at Valley Elementary approved.

· The design team is working on addressing the comments for final resubmission and approval.

· Summer 2026 Preplanning

· Primary Focus for summer of 2026 is still:

· Nurse’s Suite

· First Floor Bathrooms

· Elevator Shaft

· Painting in select areas

· Some items recently added for this summer include:

· Acoustical Ceiling Tile (ACT) in select areas

· Two chair lift replacements. The vertical lift might not arrive in time to get installed this summer.

· Column enclosures at the gym and cafeteria.

· Roof replacement in select areas.

· Bentley plans to mobilize on June 25th, the day after the final day of school.

· Colliers is bringing another construction representative to the team. Martin Warrington will focus on the work at Valley Elementary and will then shift over to the Middle-High School to assist Ryan during the school year, before going back to Valley Elementary during the summer of 2027.

4.4 Forest Avenue Elementary Project Update

4.4.1 On Monday June 8th there was a schematic design estimate reconciliation meeting with HMFH's third party estimator and the team from Bentley. Reconciliation will continue through the end of next week.

4.4.2 An update will be brought to the Building Committee at the July meeting.

4.4.3 The initial estimates are a little higher than originally forecasted, but the cost is within our available funding, and the cost is expected to be within the RIDE approved MOA to secure 55% reimbursement from the state.

4.5 Master Schedule Update

4.5.1 Justin shared that a lot of the milestones didn't change, except for the building envelope completion date at the middle high school. Gilbane pulled in that date several weeks from the schedule that was submitted last month. Last month it was March 30, 2027, and they pulled that date back to February 17, 2027.

4.6 Budget Update

· Justin shared the following budget update, stating that the budget hasn’t changed since last month, but cost for the work for Forest Avenue is expected to change.

· Project Funding Available: $201,797,059

· $190,000,000 Bond Funded

· $484,308 Appropriation from General Fund

· $5,363,000 Bond Interest (as of May 4, 2026)

· $5,700,000 Bond Premium

· $249,751 NEVI Grant

· Project Budget: $200,049,925

o Middle/High School: $173,623,000

o Valley Elementary: 20,182,100

o Forest Avenue Elementary: $6,244,825 (estimated pre-design budget)

· Expenditures to Date: $53,793,300

· Contracted: $170,958,900

· Total Anticipated Costs (excluding Contingences): $189,678,500

4.7 Four Week Look Ahead

4.7.1 The MS/HS project will continue with exterior utilities & drainage, concrete slabs, Air Vapor Barrier, exterior masonry, roofing, spray fireproofing, interior & exterior framing and MEP fire protection rough-in.

4.7.2 Valley Elementary Summer 2026 Preplanning will continue, followed by mobilization, abatement, demolition, framing, MEP fire protection rough-In and roofing.

4.7.3 Work will continue on the Forest Avenue Elementary School RIDE Schematic Design submission and Design Development phase.

4.7.4 The update from Colliers can be viewed here: https://drive.google.com/file/d/1mpWb8vsDlDiVCYAA2yAtjmqlNyvLxMhQ/view?usp=sharing.

5.1 MSHS Welding Shop CTE Program Update

· Superintendent Niemeyer informed the Building Committee that he will be meeting with a donor on Monday to discuss funding for the implementation phase of the project.

5.2 Cultural, Historical, Memorial Subcommittee Update

· Bill Nash stated that the committee continues to meet with the design team. Colors for the floors, paint, and tile have been made and graphics have been reviewed.

· Bill added that the subcommittee has met with families of those who have been memorialized in the schools, such as the Gaudet school, Clark gymnasium and Krupowicz planetarium, and the plan will be to continue with some sort of memorial in the future middle-high school.

· A more comprehensive update will be brought to the next building committee meeting.

5.3 Four Week Look Ahead

· The next Building Committee meeting will be on July 15th at 4:30pm.

Adjournment:

· MOTION: Tom Welch moved for the Building Committee to adjourn at 5:18pm and Peter Connerton seconded. The motion passed unanimously (13-0).

Respectfully Submitted,

Don Morin